Bond Project Update
Westwood Intermediate School
At Westwood Intermediate, the summer project included new air handling systems in all of the classrooms to provide a healthier, more consistent air exchange. The district also abated asbestos floor tiles in the classrooms and installed carpeting. Thirty-five year-old casework was also replaced in the classrooms. The district upgraded the plumbing and replaced rusted, hollow metal windows. Finally, the district made the bathrooms fully handicap accessible.
Multimedia
Construction Bids
Building Highlights
- Auto drop off will be separate from the bus drop off. Driving lanes could be widened to provide for two-way traffic. The new configuration will provide greater safety.
- Additional classrooms
- New service entrance for the kitchen
- Lunchroom expanded by 50 percent, ceiling raised
- Modifications to gymnasiums and academic areas
- Current cafeteria will be converted into classroom space
- Many windows will be replaced
- Installation of larger louvers will provide more fresh air
- Roof will be replaced in its entirety
-
Westwood Intermediate and Westwood Middle Schools will share the same entrance area, but each will have separate and distinct reception and office areas.
- Service corridor will be incorporated between the two gyms
- Lockers will be incorporated inside classrooms
-
Media center expansion
-
Deferred maintenance items will include:
- new air handling systems in classrooms
- new finishes on floors
- abate asbestos floor tile in classrooms and replace with carpeting
- modifications to classroom casework
- all bathrooms fully handicap-accessible
- upgraded plumbing
- upgraded finishes and lighting
- boiler room systems and chillers replaced
-
windows replaced
-
Summer 2007 construction costs at the Westwood complex: $9.8 million
| Phase Chart
Site Plan
|
Main Level - Overall
Main Level - New Addition
New combined WWI and WMS entrance
|
|

|